PEC operator categories O-6 to O-A: limits, credit points and engineers
The PEC operator ladder from O-6 to O-A: the project limit, credit points, engineers and council fee for each category.
01What limit does each operator category carry?
An operator category sets the capital cost of project the firm may take on. Table ‘B’ of the guidelines prints these limits in million rupees:
- O-6: up to 20 · O-5: up to 30
- O-4: up to 100 · O-3: up to 200
- O-2: up to 500 · O-1: up to 1,000
- O-B: up to 2,000 · O-A: no limit
Do not assume the two ladders match. Constructor C-6 carries a PKR 25 million limit under Table ‘A’, while operator O-6 carries PKR 20 million under Table ‘B’. Work beyond the limit of a licence is misconduct under the penalty table in para 27.
This part is market practice, not a PEC rule: choose the category by the largest single project you expect to take on, not by your average contract size. A higher category later needs work orders of its own (see below), so it does not come for free.
02How many credit points and engineers does each category need?
Each category sets a minimum of professional credit points (PCPs) and a staffing rule. Trainee engineers are compulsory at O-2, O-1, O-B and O-A under para 21. From Table ‘B’:
- O-6 and O-5: 5 PCPs and one registered engineer (R.E.)
- O-4: 15 PCPs and 50% registered engineers
- O-3: 20 PCPs and 50% registered engineers
- O-2: 35 PCPs, one professional engineer (P.E.) and R.E.s, with one trainee
- O-1: 75 PCPs and two P.E.s with ten years’ experience each, with two trainees
- O-B: 100 PCPs and two P.E.s with fifteen years’ experience each, with three trainees
- O-A: 150 PCPs and two P.E.s with twenty years’ experience each, with five trainees
Every employed engineer goes through biometric verification at a NADRA e-Sahulat franchise, after an attachment code arrives by SMS. The online application is submitted only once all employed engineers are done (para 12), so confirm each engineer’s attachment before you start the file.
03What does each operator category cost?
For a new registration, para 24(ii) fixes the council fee at PKR 15,000 for O-6, PKR 30,000 for O-5, PKR 45,000 for O-4 and PKR 75,000 for O-3. The operator fee table in para 25(ii) carries the higher rungs: PKR 125,000 for O-2, 150,000 for O-1, 250,000 for O-B and 400,000 for O-A.
Moving up more than one step costs more. Under para 25, one step up is charged the fee of the desired category, two steps cost twice that and three or more steps cost three times. An upgrade also needs performance evidence: under para 9(a), a one-step upgrade needs work orders worth at least 70% of the current category limit.
Fees and limits change with Governing Body decisions, so confirm the live challan on the PEC portal before you pay.
PKR 20 million for the capital cost of a project, under Table ‘B’ of PEC’s Registration Policy 2017, amended upto June 28, 2024. The constructor C-6 limit is PKR 25 million.
O-A. Table ‘B’ gives it no limit, and it needs 150 PCPs, two professional engineers with twenty years’ experience each, and five trainee engineers.
Five PCPs and one registered engineer, under Table ‘B’.
PKR 15,000, under para 24(ii) of the guidelines. Confirm the amount on the live challan before you pay.
More from the blog
- PEC3 min readPEC Registration for Contractors in Pakistan: The Complete GuideConstructor, operator or consulting — which track, which category, which papers, and how long a new PEC firm registration really takes.2026-10-05Read
- PEC2 min readPEC Contractor Categories C-6 to C-A: Limits, Fees and RequirementsEvery rung of the PEC constructor ladder — project limit, credit points, engineers and council fee — from the published schedule.2026-10-05Read
- PEC2 min readPEC Licence Renewal: Documents, Timeline and Mistakes to AvoidWhat to check before you pay the renewal challan, the documents PEC asks for, and why the last week of the licence year is the worst time to file.2026-10-05Read
- PEC2 min readHow to Upgrade Your PEC Category (and What It Really Costs)Work orders, engineers, credit points and the destination fee — what PEC looks at when you move up the ladder, and why multi-step jumps cost more.2026-10-05Read