01What limit does each operator category carry?

An operator category sets the capital cost of project the firm may take on. Table ‘B’ of the guidelines prints these limits in million rupees:

  • O-6: up to 20 · O-5: up to 30
  • O-4: up to 100 · O-3: up to 200
  • O-2: up to 500 · O-1: up to 1,000
  • O-B: up to 2,000 · O-A: no limit

Do not assume the two ladders match. Constructor C-6 carries a PKR 25 million limit under Table ‘A’, while operator O-6 carries PKR 20 million under Table ‘B’. Work beyond the limit of a licence is misconduct under the penalty table in para 27.

This part is market practice, not a PEC rule: choose the category by the largest single project you expect to take on, not by your average contract size. A higher category later needs work orders of its own (see below), so it does not come for free.

02How many credit points and engineers does each category need?

Each category sets a minimum of professional credit points (PCPs) and a staffing rule. Trainee engineers are compulsory at O-2, O-1, O-B and O-A under para 21. From Table ‘B’:

  • O-6 and O-5: 5 PCPs and one registered engineer (R.E.)
  • O-4: 15 PCPs and 50% registered engineers
  • O-3: 20 PCPs and 50% registered engineers
  • O-2: 35 PCPs, one professional engineer (P.E.) and R.E.s, with one trainee
  • O-1: 75 PCPs and two P.E.s with ten years’ experience each, with two trainees
  • O-B: 100 PCPs and two P.E.s with fifteen years’ experience each, with three trainees
  • O-A: 150 PCPs and two P.E.s with twenty years’ experience each, with five trainees

Every employed engineer goes through biometric verification at a NADRA e-Sahulat franchise, after an attachment code arrives by SMS. The online application is submitted only once all employed engineers are done (para 12), so confirm each engineer’s attachment before you start the file.

03What does each operator category cost?

For a new registration, para 24(ii) fixes the council fee at PKR 15,000 for O-6, PKR 30,000 for O-5, PKR 45,000 for O-4 and PKR 75,000 for O-3. The operator fee table in para 25(ii) carries the higher rungs: PKR 125,000 for O-2, 150,000 for O-1, 250,000 for O-B and 400,000 for O-A.

Moving up more than one step costs more. Under para 25, one step up is charged the fee of the desired category, two steps cost twice that and three or more steps cost three times. An upgrade also needs performance evidence: under para 9(a), a one-step upgrade needs work orders worth at least 70% of the current category limit.

Fees and limits change with Governing Body decisions, so confirm the live challan on the PEC portal before you pay.

Have a file like this? Send it to the desk.Ask the desk
PEC

Quick answers

The questions every new client asks.

  • PKR 20 million for the capital cost of a project, under Table ‘B’ of PEC’s Registration Policy 2017, amended upto June 28, 2024. The constructor C-6 limit is PKR 25 million.