PEC Contractor Categories C-6 to C-A: Limits, Fees and Requirements

Every rung of the PEC constructor ladder — project limit, credit points, engineers and council fee — from the published schedule.

PEC2 min read

01The ladder at a glance

  • C-6 — up to PKR 25M per project · 5 PCPs · one registered engineer · fee PKR 15,000
  • C-5 — up to PKR 65M · 5 PCPs · one registered engineer · fee PKR 30,000
  • C-4 — up to PKR 200M · 15 PCPs · 50% registered engineers · fee PKR 45,000
  • C-3 — up to PKR 500M · 20 PCPs · 50% registered engineers · fee PKR 75,000
  • C-2 — up to PKR 1,000M · 35 PCPs · one professional engineer plus registered engineers · fee PKR 125,000
  • C-1 — up to PKR 2,500M · 90 PCPs · two professional engineers (10 years each) plus registered engineers · fee PKR 150,000
  • C-B — up to PKR 4,000M · 120 PCPs · two professional engineers (15 years each) · fee PKR 250,000
  • C-A — no published upper limit · 200 PCPs · two professional engineers (20 years each) · fee PKR 400,000

02What the project limit means

The project limit is the largest single contract your category lets you bid for. A C-6 firm can bid a PKR 20 million job but not a PKR 40 million one; for that it needs C-5. Procuring agencies check this against the tender value, so the category has to be right before you bid, not after.

03Professional credit points (PCPs)

PCPs come from the engineers attached to your firm. Each category needs a minimum total, and the requirement climbs steeply at the top: 5 at C-6, 35 at C-2, 200 at C-A. Upgrades usually stall on PCPs and engineers rather than on money.

04Net worth is no longer a requirement

Older schedules listed a minimum net worth for each category. PEC abolished net worth based registration and upgradation for applications after February 2, 2022 (Registration Policy, amended upto June 28, 2024), so net worth no longer decides your category. You show finances with a bank statement for the last year, or accounts verified by a Chartered Accountant, or an audited financial statement; see our guide to PEC net worth and financial documents.

05Where these numbers come from

Limits, PCPs, engineer requirements and council fees follow the PEC constructor schedule published on pec.org.pk, cited effective 1 January 2017 unless PEC notifies a new schedule. Alqaim Engineers does not set these numbers. Confirm the live challan on the official portal before you pay.

Have a file like this? Send it to the desk.Ask the desk
PEC

Quick answers

The questions every new client asks.

  • C-6 is the entry constructor category with a published limit of PKR 25 million per project; C-A has no published upper limit and needs far more credit points and senior engineers.