01What happens to the firm when a registered engineer leaves?
Paragraph 7 of PEC’s Registration Policy 2017 guidelines (amended upto June 28, 2024) splits the case in two. Which one applies depends on whether the firm still meets its minimum PCPs and codes:
- Engineer quits, minimum still met: PEC does not ask for the original licence. The engineer is removed from the database and PEC writes to the firm about the change of staff.
- Trainee engineer quits, minimum still met: the same treatment as above.
- Engineer quits and the minimum PCPs or codes fall short: PEC asks the firm to return the original licence, and a letter tells it to complete the mandatory requirements.
02Can the engineer join another firm straight away?
Not always. Under the policy’s single-opportunity rule, an engineer gets only one employment opportunity with constructor or operator firms in a financial year, for up to three years. After resigning or being removed, the engineer is not allowed another opportunity in that year. The rule exists so that other engineers get a chance and field experience. The renewal clause ties each financial year to 1 July (para 8), so check with PEC how the year is counted before you plan a move. If an engineer was attached by mistake and the name is not printed on the licence, it is detached on request and the engineer can be attached elsewhere.
03What if the engineer is a partner or shareholder?
Engineer-owned firms follow their own rules in paragraph 5 of the guidelines:
- A firm registered on an engineer partner’s basis may replace that engineer once, with an engineer of equal experience.
- If the engineer quits and cannot be replaced, the firm stays in its category only with verifiable work orders from the last three years worth at least 70% of its lower category, with at least 60% completion. Otherwise it is closed or deregistered.
- A firm upgraded on the engineer’s ownership returns to its earlier category when the engineer quits. It may apply once more with another engineer partner, and then no further engineer-based upgrade is allowed.
- If the engineer dies or is incapacitated, the legal heirs take the share and the category stays, but the firm becomes non-engineer owned.
04Is an NOC from the old firm required?
The policy text we hold does not mention an NOC. Our document list asks for one from the previous firm when the engineer’s card still shows against it. That is our checklist, not a PEC rule, so confirm what the portal asks for on the day you file. The steps the policy does set are the new appointment papers, the engineer’s acceptance, and biometric verification with a PEC Attachment Code, which is sent by SMS from 8138 and valid for five days.
Guidelines change by Governing Body decision, so check the current policy on pec.org.pk before you act.
Yes, if it still meets the minimum PCPs and codes under Table A and B. PEC then removes the engineer from its database and writes to the firm. If the minimum is no longer met, the firm must return its licence and complete the requirement.
Under the single-opportunity rule, an engineer gets one employment opportunity in a financial year. After resigning or being removed, the engineer cannot take another in that year. Confirm how the financial year is counted with PEC.
The PEC policy text we hold does not mention one. Our checklist asks for it when the card still shows against the old firm. Confirm the portal’s current list before you file.
A firm registered on an engineer partnership may replace the engineer once with one of equal experience. If it cannot, it keeps its category only with verifiable work orders from the last three years worth at least 70% of its lower category, at 60% completion. Otherwise it is closed.
More from the blog
- PEC3 min readPEC Registration for Contractors in Pakistan: The Complete GuideConstructor, operator or consulting — which track, which category, which papers, and how long a new PEC firm registration really takes.2026-10-05Read
- PEC2 min readPEC Contractor Categories C-6 to C-A: Limits, Fees and RequirementsEvery rung of the PEC constructor ladder — project limit, credit points, engineers and council fee — from the published schedule.2026-10-05Read
- PEC2 min readPEC Licence Renewal: Documents, Timeline and Mistakes to AvoidWhat to check before you pay the renewal challan, the documents PEC asks for, and why the last week of the licence year is the worst time to file.2026-10-05Read
- PEC2 min readHow to Upgrade Your PEC Category (and What It Really Costs)Work orders, engineers, credit points and the destination fee — what PEC looks at when you move up the ladder, and why multi-step jumps cost more.2026-10-05Read